Subscribe for updates
Recent Posts
- D.C. Circuit Issues Surprise Holding in NEPA Dispute: CEQ Regulations are Non-Binding
- New Mexico District Court Applies Pro-Rata Method to Settlement under CERCLA
- New Jersey Appellate Division Finds The New Jersey Constitution Does Not Provide A Fundamental Right To “A Stable Environment”
- Wisconsin District Court Allocates CERCLA Liability for Past and Future Response Costs
- Missouri Court Rejects "Bright-Line" Test for Determining Statute of Limitations Under CERCLA Section 107
Topics
- Council on Environmental Quality
- Loper Bright
- Agency Action
- New Jersey Civil Rights Act
- Public Trust Doctrine
- Title VI
- Disparate Impact
- Environmental Justice
- Massachusetts
- Evidence
- Internal Investigation
- Citizens Suit
- Georgia
- Federal Insecticide, Fungicide, and Rodenticide Act
- FIFRA
- Major Questions Doctrine
- Lead Paint
- Greenwashing
- Good Faith Settlement
- Federal Facilities
- Statutory Notice
- Oil Pollution Act
- Federal Jurisdiction
- Owner Liability
- Court of Federal Claims
- Ripeness
- Renewable Fuel Standard
- Fish and Wildlife Service
- Greenhouse Gas
- Refinery
- Alaska
- Florida
- Solvents
- National Priorities List
- Vapor Intrusion
- Price-Anderson Act
- Solid Waste Management Act
- Personal Jurisdiction
- Successor Liability
- Operator Liability
- Potentially Responsible Parties
- Environmental Covenants
- Federal Circuit
- National Contingency Plan
- Divisibility
- Apportionment
- Water Pollution Control Act
- Strict Liability
- Utilities
- Public Utilities Commission
- Historic Resources
- Hydraulic Fracturing
- Water Use
- Ohio
- PFAS
- Alternative Dispute Resolution
- Arbitration
- Climate Change
- Auer Deference
- Fees
- Commonwealth Court
- West Virginia
- Forest Service
- TSCA
- Asbestos
- Martime
- Federal Tort Claims Act
- Gold King Mine
- New Mexico
- Utah
- Tribal Lands
- Delaware
- Delaware Department of Natural Resources and Environmental Control
- FERC
- National Forest Management Act
- Endangered Species Act
- Chevron Deference
- United States Supreme Court
- HSCA
- Alter Ego
- Corporate Veil
- Allocation
- Eleventh Amendment
- Delaware River Basin Commission
- Mining
- Intervention
- New Hampshire
- PCBs
- Property Damage
- Building Materials
- First Circuit
- Groundwater
- Natural Resource Damages
- Innocent Party
- Brownfields
- Brownfield
- Environmental Rights Amendment
- Pipeline Hazardous Materials Safety Administration
- PHMSA
- Effluents
- FOIA
- Sediment Sites
- EHB
- Texas
- Missouri
- Pipelines
- Injunction
- Coal Ash
- Spoliation
- Stormwater
- TMDL
- Safe Drinking Water Act
- Colorado
- Michigan
- Drinking Water
- North Carolina
- Bankruptcy
- Civil Penalties
- Clean Streams Law
- Hearing Board
- Arranger Liability
- Sovereign Immunity
- Retroactive
- Damages
- Stigma
- Property Value
- Tax assessment
- Fair Market Value
- Storage Tank
- Energy
- Electric
- Fifth Circuit
- Indemnification
- Arizona
- Ninth Circuit
- Attorney-Client
- OPRA
- Iowa
- Discovery Rule
- Fourth Circuit
- Eighth Circuit
- Taxes
- Administrative Appeals
- Preemption
- CAFA
- Freshwater Wetlands Protect Act
- Inspection
- Residential
- New York
- Pennsylvania Department of Environmental Protection
- Federal Energy Regulatory Commission
- Natural Gas Act
- HAPs
- Hazardous Air Pollutants
- Mercury
- D.C. Circuit
- Condemnation
- Takings
- Natural Gas
- Storage
- Fifth Amendment
- Flooding
- Takings Clause
- Spill Act
- Causation
- NEPA
- Interior
- Tenth Circuit
- Mineral Leasing Act
- California
- Act 13
- Zoning
- Duty to Defend
- Insurance Coverage
- Eminent Domain
- Landfill
- Private Right of Action
- Sixth Circuit
- Water
- Illinois
- Citizen Suit
- Diligent Prosecution
- Subject Matter Jurisdiction
- Arkansas
- Pennsylvania
- Press
- Uncategorized
- Maryland
- Eleventh Circuit
- Montana
- Navigability
- Riverbed
- Equal-Footing Doctrine
- Indiana
- Seventh Circuit
- Breach of Contract
- Public Lands
- Bona Fide Prospective Purchaser
- Green House Counsel
- Enforcement
- Equity
- Laches
- Delay Notice
- EPA
- Boiler MACT
- Consent Decree
- Rulemaking
- CISWI
- Contribution
- Declaratory Relief
- Second Circuit
- NPDES
- Procedure
- Standing
- Dimock
- Medical Monitoring
- Legislation
- Case Update
- Certification
- Contamination
- Dukes
- Louisiana
- CLE
- Cases to Watch
- Discovery
- Expert Witness
- Privilege
- Work Product
- Decisions of Note
- CERCLA
- Cost Recovery
- Defense Costs
- Insurance
- Real Estate
- Consultant Liability
- Negligence
- Remediation
- Response Action Contractors
- Army Corps
- Donovan
- Rapanos
- Nuisance
- Class Actions
- Odors
- Trespass
- Farming
- Hog Barn
- Kentucky
- Informal Agency Action
- Administrative Hearing
- New Jersey
- ISRA
- Cancer
- Combustion
- Emissions
- Railroad
- RCRA
- Waste
- Air
- Speaking Engagements
- Federal Procedure
- Removal
- Third Circuit
- Toxic Torts
- Title V
- Clean Air Act
- Permits
- Statute of Limitations
- Cleanup
- Superfund
- Supreme Court
- Multi-District Litigation
- Statute of Repose
- Tolling
- Camp Lejeune
- Wetlands
- Administrative Procedures Act
- Deeds
- Clean Water Act
- Marcellus Shale
- Due Process
- Mineral Rights
- Enforcement Action
- Oil and Gas
- Royalties
- Drilling
- Exploration
- Leases
Blog editor
Blog Contributors
In an opinion issued on February 12, 2018 in the case of Cooper Crouse-Hinds LLC et al. v. City of Syracuse et al., Case No. 5:16-cv-01201 (N.D.N.Y. Feb. 12, 2018), Judge Mae D’Agostino of the United States District Court for the Northern District of New York weighed in on the issue of when state court orders for removal and remediation resolve a potentially responsible party's liability to the government under Section 113 of CERCLA, and in this case allowing, for at least the time being, Section 107 claims to proceed where there was no clear guidance from the Second Circuit.
Cooper Crouse-Hinds involves a former landfill in Syracuse that was owned and operated by predecessors of the plaintiffs Cooper Crouse-Hinds (CCH) and Cooper Industries (CI). In the early 1960's the landfill was utilized by the City of Syracuse, and in 1972 a portion of the landfill was transferred to the County of Onodaga. In 1985 the landfill was designated as a hazardous waste disposal site under New York's version of CERCLA.
In 2004, CI entered into a Consent Order with the New York State Department of Environmental Conservation (NYSDEC) for investigation and removal activities, and in 2011, CCH entered into a Consent Order with NYSDEC for remediation of the Site. The 2004 Order did not release CI from liability but, instead, stated that nothing in the Order "shall be construed as barring, diminishing, adjudicating or in any way affecting any of [NYSDEC's] rights." The 2011 Order provided that CCH's liability would be resolved "[u]pon [NYSDEC's] issuance of a Certificate of Completion."
In October of 2016, after investigation, removal and clean-up costs of approximately $12 million had been incurred, CCH filed a complaint against Syracuse and Onodaga to recover at least some of those amounts, which Complaint was later amended to add CI as a Plaintiff. Among other things, the Plaintiffs filed both CERCLA Section 107 and Section 113 claims against the Defendants, who in turn moved to dismiss the 107 claims on the basis that the Consent Orders resolved the Plaintiffs’ liability under CERCLA, leaving them with only contribution claims. Defendants also argued that the CERCLA Section 113 claims for costs incurred under the 2004 Consent Order were time-barred as being brought more than three years after entry of the Consent Orders.[1]
The Court denied the Motion to Dismiss the 107 claims. The Court found that the 2004 Consent Order, which explicitly reserved all of the State’s rights, did not resolve CI’s liability and that the 2011 Consent Order did not necessarily resolve CCH’s liability because the release was contingent upon the issuance of Certificate of Completion by NYSDEC, which had not yet occurred. As to the latter Order, the Court recognized that there was a split in authority on whether such a conditional release triggered a Section 113 claim and if so, when, and thus allowed the claim to go forward only because “[t]he parties did not brief [the] issue,” leaving open the possibility that the claim may later be dismissed.
With respect to CI's 113 claim, the Court held that because CI had not resolved its liability to the government in the 2004 Consent Order, the limitations period for any 113 claim had not yet run. But in coming to that conclusion, the Court also questioned whether CI even had a 113 claim, given the Court's ruling that CI had not resolved its liability to the government in either Consent Order. On that issue, the Court directed the parties to further brief the issue as to why CI’s 113 claim should not be dismissed.
[1] The Parties had entered into a tolling agreement within three years of the issuance of the 2011 Consent Order. The Court also addressed the Defendant's challenges to the viability of the Plaintiffs’ state law claims, which is not the subject of this blog post.